INSPECTION AND TEST PLAN (ITP)

Fireproofing Safety Submittels

INSPECTION AND TEST PLAN (ITP)

Inspection and Test Plan (ITP) - Fireproofing Operations

🔍 INSPECTION AND TEST PLAN (ITP)

Fireproofing Operations — ASTM E605, E736, IBC Chapter 7

1. Purpose

2. ITP Matrix - Fireproofing Operations

#ActivityInspection/TestAcceptance CriteriaFrequencyResponsibilityWitness / Hold
1Material ReceivingVerify product, batch, expiration
2Material StorageTemp, humidity, off concrete
3Surface PreparationClean, dry, no rust/oil
4Primer Application (if required)DFT, coverage
5Steel TemperatureMin/max per manufacturer
6Ambient Temp / HumidityMin/max per manufacturer
7Equipment CalibrationPressure, nozzle, flow
8Wet Film Thickness (WFT)Max per pass
9Coverage Rateft²/gal or ft²/bag
10Visual - During ApplicationNo slump, runs, gaps
11Environmental MonitoringSteel temp, air temp, RH
12Dry Film Thickness (DFT)Per ASTM E605
13Visual Inspection - FinalNo defects, cracks, spalls
14Density Test (cementitious)Per ASTM E605
15Adhesion Test (pull-off)Per ASTM E736
16Final AcceptanceAll tests passed

3. Hold Points & Witness Points

Definitions:
Hold Point: Work cannot proceed without inspection. Notify GC/Inspector; wait for approval.
Witness Point: Inspection required; work may continue but inspector must be present.

3.1 Hold Points (Work Stops)

#Hold PointNotification TimeApproval Required From
1Material receiving
2Primer application
3Adhesion testing
4Final acceptance

3.2 Witness Points (Inspection Required)

#Witness PointNotification Time
1Surface preparation
2DFT testing
3Density testing (if required)

4. Inspection & Test Equipment

EquipmentCalibration RequiredFrequencyCalibration Due
WFT gauge (comb)NoReplace when wornN/A
DFT gauge (electronic)YesAnnual
Pull-off adhesion testerYesAnnual
Infrared thermometerYesAnnual
Hygrometer / thermometerYesAnnual

5. ITP Log Entry

6. Non-Conformance & Corrective Action (ITP Integration)

StepActionResponsible
1Fail inspection or testQC Inspector
2Issue Non-Conformance Report (NCR)QC Inspector
3Notify Superintendent and GCQC Inspector
4Determine root causeSuperintendent
5Implement corrective actionApplicator
6Re-inspectQC Inspector
7Close NCRSuperintendent

7. Inspection & Test Record Retention

RecordRetentionResponsible
Completed ITP LogsProject duration + 5 years
Calibration certificatesCurrent + 1 year after expiration
Third-party test reportsPermanent
Non-Conformance ReportsProject duration + 5 years

8. Approval Signatures

✅ Fillable Inspection and Test Plan — Complete all sections, then click "Save as PDF / Print" and choose "Save as PDF" to generate a permanent record. This ITP is specific to fireproofing operations per ASTM standards. Hold points require work stoppage until inspection approval.